Carhartt Indiana

Greenwood, IN

Synergy Construction completed an interior build-out of a Carhartt store in the Greenwood Park Mall in Indianapolis, Indiana. In order to avoid disruption of the mall we completed the removal of the existing fa├žade and installed new materials all after hours. Synergy completed this project in two months.

Project in BriefInterior Build-out of retail space

Project Duration
2 Months

Budget

$350,000

Size
3,400 SF

Team
Synergy Construction Group
RGLA